FRP procurement checklist
Use this interactive list during your buying process. Check each item off as you validate it with the supplier — your progress is saved in this browser so you can resume the evaluation.
Before issuing an RFQ
Define your requirements
- Why it matters
Include pH, operating temperature, seasonal variations. A common error is specifying only "wastewater" when the fluid contains chlorides, sulfates, or cleaning chemicals.
- Why it matters
Include water hammer peaks, start-stop transients. Typical safety factor is 1.5×.
- Why it matters
Wind, seismic, weight of upper structures, ice/snow loads if applicable. Attach a drawing with details.
- Why it matters
If the process has cold-hot cycles or continuous vibration, specify it. Affects resin choice and anchor design.
Questions the quote must answer
Technical questions to require
- Why it matters
Don't accept generic "vinyl ester". Require commercial name (e.g. Derakane 411-45, Hetron 922) and a commitment to use that lot.
- Why it matters
The chemical barrier typically requires a different (usually more resistant) resin than the structural layer. Require it to be specified separately — brand, product, and its chemical resistance to your process fluid.
- Why it matters
Must detail: nominal barrier thickness (typically 2.5–4 mm), surface veil used, number of mat plies, and resin/fiber ratio in this layer. This is the component that most determines service life.
- Why it matters
For structural loads the typical factor is 5:1 in FRP (vs 3:1 in steel); for internal pressure 5:1 – 10:1 depending on code. Require it to appear explicitly in the design calculation memo.
- Why it matters
Filament winding for the body, hand lay-up for heads/nozzles. Ask for a zone diagram with process noted.
- Why it matters
Must specify: minimum thickness per zone, measurement method (ultrasonic), and measurement locations.
- Why it matters
Minimum 35–40 for vinyl ester. Must include a report with readings at 5+ points.
- Why it matters
ASME RTP-1, BS 4994, or other. Confirm the design was calculated (not copied) for your case.
- Why it matters
PDF copies of ASME RTP-1, ISO 9001, ASTM, with expiration dates. Verify they aren't expired.
Contract terms to negotiate
Contract clauses
- Why it matters
With 3–5 business days notice. Key points: body lamination, head lamination, curing, final tests.
- Why it matters
Some serious suppliers offer 5 years on structural laminate. That's a confidence signal.
- Why it matters
Includes: dimensional, hydrostatic, Barcol hardness, ultrasonic thickness, visual inspection, resin COA.
- Why it matters
Final dimensional drawing with modifications, installation manual, maintenance manual, spare parts list (if applicable).
- Why it matters
Right to hire a third party (like PITSA) for inspection before accepting. No price retaliation.
- Why it matters
Avoid 100% against delivery. Example: 30% advance, 40% against verified progress, 30% against acceptance after inspection.
A supplier who resists signing any of these points is telling you something important. Take note and push back — or find another.
Draft. Tune to your procurement policy and corporate governance system.