Inspection checklist
This list is for on-site use when receiving an FRP tank, pipe or duct. Use it as a reference and check each item off — your progress is saved locally.
Receiving FRP equipment
- Why it matters
Measure with ultrasonic at 5+ points (body, heads, connection zones). Typical tolerance: ±5% of design. Record values in signed report.
- Why it matters
Visual inspection under good lighting. No bubbles, craters or thin zones. For critical service, low-voltage holiday test.
- Why it matters
Multiple points with Barcol durometer. Typical: ≥ 35–40 for vinyl ester. Low reading indicates incomplete cure.
- Why it matters
Copy of Certificate of Analysis (COA) for the resin lot used. Must match spec on PO.
- Why it matters
Overall dimensions, out-of-roundness, flange flatness, nozzle alignment. All within ASME RTP-1 or applicable standard.
- Why it matters
No cracks, delamination, cure hot spots (burns) or contamination. Heads and secondary bonds firm to touch.
- Why it matters
Data plate with manufacturer, date, resin, design thickness, design pressure/vacuum, temperature, certifications.
Draft. Tune items to your specific process.